The LADBS Rebuild Permit Process, Step by Step
Permits are moving three times faster than before the fire. Most lots are still empty. Here is why, and the exact order to do things in.
Where things actually stand
Permitting in the Palisades is moving far faster than normal Los Angeles construction — the City has reported rebuild permits being approved close to three times faster than single-family projects before the fire, with more than 70 percent of single-family permit clearances no longer required at all. The first Certificate of Occupancy for a rebuilt Palisades home was issued in November 2025.
And yet most lots are still empty. That is not a contradiction. The permitting pathway got dramatically faster, but the work before the permit application — insurance settlement, design, soils, engineering, financing — is where nearly everyone is stuck. Understanding the sequence is how you stop losing months.
The sequence, in order
Step 1 — Confirm your lot is cleared
Army Corps of Engineers debris removal has been completed across most of the burn area. Lots that opted out and used private clearance have had varying timelines. Confirm your specific parcel's clearance status with LA County before you spend money on anything else.
Step 2 — Soils and geotechnical
On most Palisades lots this gates the entire project, because it determines your foundation design, which determines your structural drawings, which determine your budget. Start it early. Homeowners who wait on this lose entire quarters.
Step 3 — Choose your design path
Two doors. A custom set of drawings from your own architect, or one of the City's pre-approved standard plans through the Standard Plan Pilot Program. The standard plan route trades design freedom for speed and predictability. Either way, decide before drawings start whether you are rebuilding like-for-like or materially changing the envelope, because that choice determines which review pathway you fall into.
Step 4 — Assemble the plan package
Architectural, structural, civil, Title 24 energy, and the reports supporting them. Incomplete packages are the number one cause of plan check delay, and every round trip costs weeks.
Step 5 — Submit to LADBS
Two routes: online through the EPIC-LA / eplan portal, or in person at the One-Stop Rebuilding Center at 1828 W. Sawtelle Blvd, Los Angeles, CA 90025. For complicated lots, the in-person route is often worth the trip — you get triage and direct answers instead of an emailed correction list.
Step 6 — Plan check and corrections
Expect at least one correction cycle. Recent LADBS data analyzed publicly put the average wait from application to permit at roughly 49 days across all permit types. Well-prepared packages land near the low end; incomplete ones far exceed it.
Step 7 — Permit issued, then build
Two deadlines to write down. To qualify for the Executive Order 1 streamlined path, permits must be obtained before January 13, 2032. And once your permit is issued, you have three years to complete the rebuild. Missing the 2032 date means losing the fee waivers, the expedited review, and the other fire-specific benefits. Inspections run throughout, and the final step is your Certificate of Occupancy.
One more protection worth knowing: LADBS targets 30 business days to review a complete application, and under AB 253, if they miss that window you may use a third-party reviewer. Most homeowners have never heard of this.
Fees and relief worth knowing about
- Permit fees are waived, not just suspended. Mayor Bass's Emergency Executive Order 7 suspended collection, and the City has since moved to a fee waiver ordinance. The waivers are capped at an aggregate $90 million over three years and apply only to individuals or entities that owned the property on January 7, 2025. LADBS has been working out procedures to refund fees already paid on qualifying projects — if you paid, ask about a refund.
- Building code vintage. The Governor suspended the 2025/2026 building codes for this rebuild, allowing homeowners to build to the more familiar 2022 California Building Code.
- Property tax. AB 245 extended property tax relief for victims of the 2025 fires, giving affected owners additional years to complete a like-for-like rebuild while retaining their prior base year value.
- SB 9 does not apply here. Emergency Executive Order 9, issued July 30, 2025, prohibits SB 9 urban lot splits and duplexes within the Very High Fire Hazard Severity Zone inside the Palisades fire boundaries. Do not plan around it. ADUs are a separate question and are still available.
- The 110 percent rule. You may increase footprint and height by up to 10 percent and stay inside the streamlined pathway. Exceeding 110 percent triggers the full 2025 California Building Code. Executive Order 8 does extend streamlining to zoning-compliant non-like-for-like projects, but the code question is separate from the streamlining question.
Resources we actually point clients to
- One-Stop Rebuilding Center — 1828 W. Sawtelle Blvd, Los Angeles, CA 90025. In-person permit triage and plan check coordination.
- LADBS homeowner rebuild information — the authoritative source for standard plans, fee suspension, and submittal routes.
- LADWP Unified Utilities Rebuild Operations Center — coordinates water and power restoration.
- Pacific Palisades Community Council — community rebuilding bulletins and neighborhood-level updates.
- PaliBuilds — homeowner-facing rebuild information and cost data.
The mistakes that cost the most time
- Waiting on the insurance settlement before starting design and soils. These can run in parallel, and running them in sequence costs you six months or more.
- Submitting an incomplete package to save two weeks, then losing eight in corrections.
- Deciding to expand the footprint after drawings are underway, and falling out of the streamlined pathway.
- Hiring a builder who has never worked through LADBS plan check on a fire rebuild and is learning the process on your project.
Frequently asked questions
How long does a Palisades rebuild permit take in 2026?
Publicly analyzed LADBS data put the average from application to permit at roughly 49 days across permit types, and rebuild permits are being approved close to three times faster than pre-fire single-family projects. A complete, well-prepared package lands near the fast end. The bigger delay for most homeowners is the design, soils, and engineering work that happens before submittal.
Do I have to pay LADBS permit fees to rebuild?
Permit fee collection has been suspended for projects repairing, restoring, demolishing, or replacing property substantially damaged or destroyed by the wildfires, for owners who held the property on or before January 7, 2025. Confirm your specific eligibility with LADBS.
Which building code do I have to build to?
The Governor suspended the 2025/2026 building codes for this rebuild, allowing homeowners to build to the 2022 California Building Code. Note that fire-hardening requirements under the updated Wildland-Urban Interface standards still apply.
Is there a deadline to rebuild?
Two. Permits must be obtained before January 13, 2032 to qualify for the streamlined pathway, and once your permit is issued you have three years to complete the project.
Can I split my lot or add a duplex under SB 9?
No. SB 9 urban lot splits and duplexes on single-family lots have been banned within the Palisades fire burn area by executive order. ADUs are a separate question worth asking your architect about.
About this guide
This page is general information for homeowners, not legal, insurance, or engineering advice. Codes, executive orders, and agency procedures related to the January 2025 wildfires have changed repeatedly and may have changed again since this page was updated. Confirm anything that affects a decision with LADBS, the City of Malibu, your insurer, or your own licensed professional.